OEE: the details
It is calculated by multiplying three factors. Availability: the time the machine was running over the planned time. Performance: actual speed against ideal speed. Quality: good parts over total parts made. A line with 90% availability, 95% performance and 98% quality has an OEE of 83.8%.
Its value is in the breakdown, not the figure. The same OEE can hide long stops, micro-stops nobody writes down or a quality problem, and each cause calls for a different action. The number is only reliable if stops and quantities are captured automatically or on the spot: an OEE calculated from reports filled in at the end of the shift usually looks better than it is.